What Should a Developer Have Ready Before Site Work Starts?

Most site work delays start before the first machine shows up. Here is the checklist developers and general contractors should clear before mobilization day.

October 17, 2026 · 6 min read

The Short Answer

  • Approved civil plans and a geotechnical report are the two documents a site contractor needs first.
  • Land disturbance, grading and stormwater permits have to be in hand before clearing starts. Sites disturbing an acre or more generally need construction stormwater permit coverage.
  • Utility locates, survey control and a clear access plan prevent the most common day-one delays.

Why does pre-construction prep matter for site work?

Site work is the first trade on the ground, so every missing permit, unanswered design question or unmarked utility lands on it first. A crew and a fleet of equipment sitting idle while paperwork catches up is expensive for everyone.

The good news is that almost all of it is predictable. These are the items Brown Bros. asks about before mobilizing on a commercial, industrial or land development job.

What documents does a site contractor need?

The essentials are a complete set of approved civil drawings (grading, drainage, utilities, erosion control) and a geotechnical report describing the soil and rock conditions. The geotech report drives how the site is excavated, whether soils can be reused as fill, and what compaction is required.

CAD or 3D surface files of the existing and proposed grades let the contractor build a machine-control model, so GPS-guided equipment can grade straight from the design.

  • Approved civil plans: grading, storm, sanitary, water and erosion control sheets
  • Geotechnical report with boring logs and fill and compaction requirements
  • Existing topographic survey and proposed surface files
  • Specifications for pipe, stone, compaction and testing

Which permits are needed before clearing and grading?

Requirements vary by city and county, but most sites need a local land disturbance or grading permit. Sites that disturb one acre or more generally need construction stormwater coverage, which in Tennessee is issued by TDEC under its Construction General Permit and in Georgia by Georgia EPD, along with a stormwater pollution prevention plan (SWPPP).

Utility tie-ins, road cuts and driveway connections usually need their own approvals from the utility or roadway owner. Starting before these are issued risks stop-work orders and fines.

What should be done on the site itself?

Call 811 so public utilities are located and marked before any digging; Tennessee and Georgia both run 811 one-call systems. Private lines on the property need a private locator. A surveyor should set control points and stake the limits of disturbance, so clearing stays inside the permitted area.

Settle the practical items too: a construction entrance and haul route, where cleared timber and spoils will go, and any trees or buffers that must be protected.

How can one contractor simplify this?

Brown Bros. self-performs surveying and land planning, clearing, erosion control, excavation, grading, utilities and paving. One contractor carrying the whole site scope means fewer handoffs between permits, layout and the dirt crews, and one point of accountability for the schedule.